Zpracování předběžné studie proveditelnosti projektu "Odběr strusky z Elektrárny Tušimice"

Abstract

This bachelor thesis deals with preliminary study of regularity project about consumption slag power station Tušimice. Purpose and turget of the study is to solve the problems of the finally storing hydraulically taken slug from power station to basins. In bachelor thesis is given description of the current liquidation process slag of power station Tušimice and there are given a new proposals about variant solution. In the next section of my work there are individually described variants of solution and their technical and economic evaluation. In the very end of my work there is specified the selected alternative solution, including his technological and operational process.

Description

Import 04/07/2011

Subject(s)

study, slag, technology, fly-ash, technical and economic evaluation, pump