Návrh projektu klimatizace porubu 40 205 dolu Darkov závod 3

Abstract

This diploma work deals with the project of forefield n. 40 205 mine air-conditioning in the Darkov Mine plant 3 (formerly the 9th May). In the theoretical part, I have described the history of the Darkov Mine plant 3, the natural circumstances of the interest area, the central air-conditioning of the Darkov Mine plant 3 and the forefield 40 205 microclimatic conditions. The still increasing depth of stoping forces TPCL us to use the air - conditionings in larger degree. In these depths the workplace microclimatic conditions rapidly deteriorate owing to the TPCL increasing temperatures of the primary rocks. In which the different work lengths on mine workplaces are calculated so that the TPCL adverse conditions have as minimal effect on the health, the effort and the load of mine forefield n. 40 205 cooling workers as possible.

Description

Import 04/07/2011

Subject(s)

microclimatic conditions, mine air - conditioning, Darkov Mine plant 3, forefield 40 205, cooling system