Time-cost schedules and project-threats indication

dc.contributor.authorKuda, František
dc.contributor.authorDlask, Petr
dc.contributor.authorTeichmann, Marek
dc.contributor.authorBeran, Václav
dc.date.accessioned2022-06-06T08:43:09Z
dc.date.available2022-06-06T08:43:09Z
dc.date.issued2022
dc.description.abstractOne of the most common disciplines in a business or economic project is timing and resource review. Despite the frequency of use, the level of sophistication is not high enough to maintain its level of importance. Exceeding deadlines and non-compliance with contractual costs is more than common. Moreover, there are projects where uncertainties are a naturally accompanying phenomenon. Research projects, implementation of solutions in a time-limited situation, or in an environment of limited knowledge creates risk. Any project proposal faces future realization risks when its planning management does not know with certainty where the current risks and uncertainties may come from. Decision-making, risk management dynamics, and simulations have developed in recent decades into an erudite and useful discipline. The aim is to indicate how much of the time-cost schedule proposal is stable, controllable, and economically feasible. The approach is based on the idea that modern resource scheduling requires nonlinear dynamic calculating models and simulations. The methodology presented is based on the dynamics of underlying physical and economic processes that form a spatial pattern of a time series. The article's objective is devoted to the early indication of a dynamic project schedule's instability and predisposition to bifurcation and chaos. In other words, the aim is to show not only what will happen but how diverse and damaging the project may become in the future.cs
dc.description.firstpageart. no. 2828cs
dc.description.issue5cs
dc.description.sourceWeb of Sciencecs
dc.description.volume14cs
dc.identifier.citationSustainability. 2022, vol. 14, issue 5, art. no. 2828.cs
dc.identifier.doi10.3390/su14052828
dc.identifier.issn2071-1050
dc.identifier.urihttp://hdl.handle.net/10084/146250
dc.identifier.wos000771365500001
dc.language.isoencs
dc.publisherMDPIcs
dc.relation.ispartofseriesSustainabilitycs
dc.relation.urihttps://doi.org/10.3390/su14052828cs
dc.rights© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.cs
dc.rights.accessopenAccesscs
dc.rights.urihttp://creativecommons.org/licenses/by/4.0/cs
dc.subjecttime schedulingcs
dc.subjectproduction speedcs
dc.subjectproduction accelerationcs
dc.subjectsimulationcs
dc.subjectproject costscs
dc.subjectdurationscs
dc.subjectrisk evaluationscs
dc.subjectcircular life cyclecs
dc.subjectmanagement dynamiccs
dc.titleTime-cost schedules and project-threats indicationcs
dc.typearticlecs
dc.type.statusPeer-reviewedcs
dc.type.versionpublishedVersioncs

Files

Original bundle

Now showing 1 - 1 out of 1 results
Loading...
Thumbnail Image
Name:
2071-1050-2022v14i5an2828.pdf
Size:
4.3 MB
Format:
Adobe Portable Document Format
Description:

License bundle

Now showing 1 - 1 out of 1 results
Loading...
Thumbnail Image
Name:
license.txt
Size:
718 B
Format:
Item-specific license agreed upon to submission
Description: